Thailand paused construction on 49 datacentre projects and delayed approval decisions on 117 others in September 2026, according to the published report This move followed growing concerns about insufficient details for regulation and monitoring of these facilities.reported
How we got here
In early 2026, Thailand’s board of investment approved datacentre projects from TikTok, Skyline Datacentre and Bridge Datacentres, totalling $27bn in planned investment.reported South-east Asia emerged as a growth centre, holding about 50% of under-construction datacentre capacity in the Asia Pacific region, per Cushman and Wakefield.reported
What is new
Construction halted in multiple jurisdictions. In Indonesia, the governor of West Java stopped a datacentre build due to lack of permits and an incomplete environmental assessment process. Thailand’s pause cited regulatory and monitoring concerns.
What to make of it
The region faces power and water constraints that are pressuring growth. Singapore implemented a moratorium on new datacentres from 2019 to 2022 due to intensive water and electricity usage.reported Since then, approvals have been selective amid land constraints.
What the rules require
Compliance for model evaluators and infrastructure planners now demands rigorous verification of local regulatory frameworks before committing capital. Evaluators must assess whether a region has sufficient regulatory detail for monitoring, as Thailand’s pause cited a lack thereof. Sustainability requirements regarding water and electricity usage, as seen in Singapore, are now baseline constraints rather than optional considerations.
Why it matters
- Regulatory pauses in Thailand and Indonesia highlight the risk of incomplete approval processes for large-scale infrastructure.
- Singapore’s long-standing moratorium and selective approvals demonstrate how resource constraints can limit expansion despite high demand.
- The shift from Singapore to Malaysia and Thailand shows how regional capacity dynamics change rapidly with new investments.
- Power and water availability remains a critical factor in determining viable locations for new datacentre construction.
Topics: datacentres, infrastructure, south-east asia, regulation
Updated
Then / now / next
Thailand approved $27bn in datacentre projects in early 2026.
Construction on 49 projects was paused in September 2026 due to regulatory concerns.
It remains unclear how long the pause will last or what new regulations will be implemented.
Story timeline
- Then Thailand approved $27bn in datacentre projects in early 2026.
- 07 Nov 2026 The datacentre arms race hits pause in south-east Asia
- Now Construction on 49 projects was paused in September 2026 due to regulatory concerns.
- Next It remains unclear how long the pause will last or what new regulations will be implemented.
For readers
Investors
- Thailand paused $27bn in planned investments due to regulatory gaps.
- Malaysia saw operational capacity grow tenfold from 2023 to 2026.
Policy
- Thailand cited insufficient details for regulation and monitoring.
- Indonesia halted a project due to incomplete environmental assessments.
Researchers
- South-east Asia holds 50% of Asia Pacific under-construction capacity.
- Singapore added only 95MW between 2023 and 2026 due to constraints.
Ask the article
Local keyword search of this article; no generated answers.Did this article give you the evidence you needed?
Your choice stays on this device. No public tally.Questions readers ask
Why did Thailand pause datacentre construction?
Thailand paused construction due to concerns about the lack of sufficient details for regulation and monitoring of the projects.
How much datacentre capacity was added in Singapore between 2023 and 2026?
Singapore added just 95MW of operational capacity between 2023 and 2026, according to Cushman and Wakefield.
Which countries hold the largest share of under-construction datacentre capacity in Asia Pacific?
South-east Asia holds about 50% of the total under-construction capacity, with Malaysia and Thailand comprising a large portion.
Connected stories
Reading receipt
- Thailand paused construction on 49 datacentre projects in September 2026.
- Indonesia’s West Java governor halted a datacentre build due to permit issues.
- Singapore added only 95MW of capacity between 2023 and 2026.
Still open: What specific regulatory details are missing in Thailand?
Still open: Will Indonesia’s West Java project resume after completing its environmental assessment?